EnvironmentLocal NewsWeather New haul-out system planned to speed vessel removals before storms by Ricardo Roberts 15/09/2026 written by Ricardo Roberts 15/09/2026 3 min read A+A- Reset Director at the Costal Zone Management Unit Dr Leo Brewster takes a look at the work done at the Fisheries Complex after hurricane Beryl devastated the area in 2024. (Photo Credit: Shamar Blunt /Barbados TODAY) FacebookTwitterLinkedinWhatsappEmail 297 Plans are underway to overhaul emergency vessel haul-out facilities in coastal areas after delays during Hurricane Beryl left boats and operators vulnerable ahead of severe weather, Coastal Zone Management Unit director Dr Leo Brewster has revealed. The redesign is part of wider climate-adaptation efforts intended to protect maritime assets, safeguard fishersโ livelihoods and strengthen coastal resilience. Future coastal construction must combine structural resilience with the ability to move vessels quickly, he said. The proposed facility would include a specialised travelift, or tummy lift, operating from a dedicated finger pier alongside a wide slipway. The design is intended to allow large commercial vessels and smaller private craft to be removed from the water at the same time during emergency preparations. Under previous arrangements, haul-out operations relied heavily on a single crane to sling, lift and clear each boat individually. This caused delays before storms, particularly when partially submerged or waterlogged vessels needed time to drain before they could be moved safely. โStructure, in terms of building โ building for resilience โ is something that we also have to give a lot of consideration for as well,โ Dr Brewster said during a tour of the Fisheries Complex. โThe intention with the travelift is supposed to be that the vessel can actually sail onto the straps. You lift it up, and then that lift moves and takes it to a location where it can then be placed on either a trailer or the supports.โ Director Coastal Zone Management Unit Dr Leo Brewster. (Photo Credit: Shamar Blunt /Barbados TODAY) The travelift would operate alongside a traditional slipway, allowing different types of vessels to be handled at the same time, he explained. You Might Be Interested In Crystal Beckles-Holder, 2nd runner up in regional competition GUYANA: Body of child found after gold mine collapses Barbadians asked to help with return tickets for Haitians โIn the meantime, thereโs also supposed to be a slipway for the smaller vessels to be able to useโto be able to, if you have a trailer for those vessels, to then have them actually come up onto those and then be taken away as well.. โSo it will provide two different opportunities to work simultaneously, instead of just having one crane thatโs going to take time to actually lift, to sling a vessel, lift it, place it, and then move it along the way.โ Authorities are also considering long-term storage through a designated onshore boat park next to the haul-out facility. Dr Brewster said the support structures must be engineered to withstand repeated heavy loads from both the travelift and vessels. โBetween having the haul-out facility, the boat park where you need to have those locations to handle the volume of vessels, weโre not at full capacity yet. โAs you can see, varying size vessels can carry different weight; therefore, you have to be able to have a support system that can handle the variation in weight repeatedly, as well as the weight of the travelift carrying not only its own weight, but the weight of the vessels itโs transporting as well.โ The success of emergency operations would also depend on owners moving their vessels early rather than waiting until a storm warning was issued, the CZMU head added, invoking the memory of the late Chief Fisheries Officer Dr Shelly-Ann Cox, who died in June.. โFrom what I remember Shelly saying, itโs about four days, as long as all the vessels are in place and they need to move, right? They have to be here,โ Dr Brewster warned regarding total lead time requirements. โIt canโt be that you determine at the last minute to come in. But if these are here, you can move them, and you can get synchronicity in what youโre doing. Hopefully, it will take about four days to move the majority โ maybe not all, but the majority โ and this is the reason why.โ (RR) Ricardo Roberts You may also like Mother testifies in sonโs murder trial 16/09/2026 Government mulls dedicated sargassum unit 16/09/2026 Study: 80 more days a year above 30 C by mid-century 16/09/2026