Home ยป Posts ยป 1MW pilot in plan to shore up power grid

1MW pilot in plan to shore up power grid

by Ricardo Roberts
6 min read
A+A-
Reset

Barbados will run a one-year, one-megawatt pilot to test whether solar installations, batteries and electric vehicles can help stabilise a power grid nearing capacity, Barbados TODAY can exclusively reveal. The trial will begin with public bodies and their partners, with private motorists waiting until officials have worked out the technical and regulatory rules for feeding electricity back into the grid.

โ€œThis pilot is only about one megawatt,โ€ said Horace Archer, a senior technical officer at the Ministry of Energy. The trial would assess systems of different sizes, from commercial-scale installations to smaller domestic-scale setups of a virtual power plant (VPP) and vehicle-to-grid (V2G) system, he said.ย ย 

โ€œThe pilot will then decide how big going forward the overall capacity will be for the virtual power plant and V2G,โ€ Archer said. โ€œThat is what this pilot will teach us going forward.โ€

Brian Haynes, director of renewable energy in the ministryโ€™s Energy Conservation and Renewable Energy Unit, said the virtual power plant would coordinate solar generation and battery storage at participating sites so the utility could draw power and collect operating data. Vehicle-to-grid technology would allow compatible electric vehicles to feed stored power back into the grid while plugged in. Haynes estimated that the approach would provide about 80 per cent of the support a utility would seek from a distributed energy resource management system, software that monitors and coordinates equipment across the grid, as the share of renewable energy grows.

โ€œIt would improve the reliability of the grid,โ€ Haynes said. โ€œIn terms of cost, yes, it will also help, once we put the appropriate regulatory frameworks in place to do that.โ€

Officials have yet to set payment formulas or tariffs for private electric vehicle owners. Haynes said any payments would be for services to the grid, not a guarantee of substantial earnings. Dr Randall Johnson, a consultant on the project, had outlined different payment and market models, including paying participants based on the support they provide.

โ€œWe often have very good ideas about what we want to do, but it comes down to how we design the regulatory [framework],โ€ Haynes said, adding that โ€œpaying by performance is one of the considerations that we are looking at going forward in this project.โ€

Haynes said the aim was to keep costs to consumers as low as possible while maintaining a reliable supply. If the utility faced a sudden shortage or needed a few extra kilowatts at certain times of day, paying a few cents more per unit could be worthwhile if it prevented an outage.

โ€œIf there is a situation where the utility needs power urgently, they may be willing to pay a little bit more for that power to stabilise it, but we donโ€™t envisage that that would become something that is extremely over the top or costly,โ€ Haynes said.

โ€œOf course, the regulator will step in to place the various caps and so on on what the possible cost would be for that stabilising energy that we will be requiring in order to promote and safeguard stability,โ€ Haynes added.

The wider project spans 24 months, including the design phase and the one-year pilot. Its findings will help shape technical and regulatory rules in consultation with the regulator and the Fair Trading Commission, as well as inform grid design and possible commercial arrangements. One option would allow motorists to plug in at supermarkets or other businesses, with the utility safely pooling the power to support the grid.

โ€œWe do envision that this would be attractive to some persons who will see this as a means of providing additional services as well as it will also provide some support to the grid and the utility will find some value as well.โ€

The ministry decided against opening the initial trial to commercial operators or private drivers. Sites identified for the pilot include the National Insurance and Social Security Service (NISSS), the University of the West Indies (UWI), the Barbados National Energy Company Limited (BNECL) and the Queenโ€™s Park solar demonstration initiative. Haynes said officials were finalising a legal framework to ensure fair and transparent arrangements across participating public bodies. Solar host partners are expected to join first, followed by additional government and BNECL participants.

Haynes said: โ€œWe considered first bringing in commercial and private entities, but we said no, let us have it in a very contained [way], keep it as controllable and small as possible first and then we can replicate as we improve.โ€

The initiative grew out of the islandโ€™s integrated resource and resiliency plan. With distributed solar photovoltaic capacity nearing 90 to 100 megawatts and the utility warning that the grid was approaching capacity, planners set out to test how battery storage, telecommunications and grid management could help stabilise a small, isolated power system.

Haynes added: โ€œWe want to understand how this type of technology or framework would operate within the Barbadian context, a small island, isolated grid; it has certain nuances to it thatโ€ฆ may not exist in other contexts.โ€

The ministry put the work out to tender with technical guidance from Johnson, Archer and the contractor Xcellerex. Xcellerex won the bid and completed the design phase around February this year.

โ€œWe want to be able to help the utility get to the place where it can get as much support in stabilising the grid as we move towards renewables; at the same time, we want to ensure that consumers benefit as much as possible,โ€ he said.

ย 

What to know: How virtual power plants and vehicle-to-grid work

  • Virtual power plant (VPP): Software links equipment at different sites, such as rooftop solar panels and batteries, so they can support the grid together. For example, batteries can store solar power during the day and release it when electricity demand rises.ย 
  • Vehicle-to-grid (V2G): A compatible electric vehicle and a two-way charger let electricity flow in both directions. The car can draw power to charge its battery or, while plugged in, send some of that stored electricity back to the grid.ย 
  • How they fit together: A virtual power plant can pool electricity from several plugged-in vehicles, but it can also work without them. Barbados plans to start with a controlled pilot before opening the scheme to private motorists. Payment rules for drivers have not yet been set.ย 
  • How they are managed: A distributed energy resource management system (DERMS) is software that helps an electricity utility monitor and coordinate equipment connected at different points on the grid, such as solar PV panels, batteries and electric vehicle chargers. For example, it can tell batteries to release stored power when demand is high or limit how much solar power flows onto a line to keep voltage within safe limits.

(RR)

You may also like

We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it. Accept Privacy Policy

-
00:00
00:00
Update Required Flash plugin
-
00:00
00:00